- nach mehreren Vermessungen des Grundstücks beginnen die Arbeiten
- Grobabsteckung: Haus – Schnurgerüst, Gartenhaus, Terrasse, Einfahrt, Kranstellplatz
- Zusatzauftrag: Befestigung Carboard, Gartenhaus, Terrasse, Einfahrt bis Carboard
- Bodenbeschaffenheit anders als erwartet : 70cm Mutterboden statt 20-30cm, kein tragfähiger Untergrund > kompletter Bodenaustausch necessary
- excavation is made, reinforced soil is replaced,
- disposal of excavation contractors performance: rich who wants to clean topsoil? From whom can you pick up the? Is it possible to sell the land? ... > Three companies mentioned, taken around> never again that which> is lack of understanding on our part: so a good ground and no one wants to LAV driven, demand, offer made> nothing to sell - and pay for the disposal! (now week 16)
- pipes are laid in sand under the foundation plate
- base plate will be tried and cast: Heavy equipment is located on the site: impressive, everything is captured on screen!
- after a day's walk on the plate already!
- way again up appointments: When will the house wie lange dauern die Montagearbeiten, wann steht der Dachstuhl, wann kann das Richtfest stattfinden? > Festlegung nach Absprache mit allen Beteiligten auf den 26.03.2010
- Schreiben an die Nachbarschaft verfassen: über Baumaßnahmen und eventuelle Behinderungen in Kenntnis setzen und zum Richtfest einladen > Organisieren!!!
Abnahme Fundamentplatte – Rechnung von „Bau mein Haus“